See below for updated information on potential impacts of the construction work.
Update 19 December, 2025
The construction site will be closed for the Christmas holiday from 22 December to 6 January.
Most of the work phases that cause the highest noise levels have now been completed. At the beginning of 2026, some drilling for pile foundations will still be carried out, which will generate noise. Noise-producing work will take place between 8:00 and 19:00. One building on the site still needs to be demolished; mechanical concrete crushing will be used during the demolition work.
Construction of the hotel foundations will begin on 7 January, after that the structural frame will get underway. The structural elements will be transported mainly via Hiihtokouluntie.
Update 6 December. 2025
The water tank and district heating modifications are now complete and the parking lot is in use for passenger cars. The hotel construction site fences will remain in place until 2027. Bus parking will continue at the stadium.

Update 5 September, 2025
Week 36/2025 (September 1–7, 2025)
Bus parking in front of the Conference Center is temporarily unavailable.
Due to modification and relocation work related to EVO’s district heating system, the large parking area in front of the Conference Center is currently not available for bus use.
Bus parking has been relocated to the Ruka Ski Stadium (address: Hiihtostadionintie 3a).
The map below shows the location of the new parking area as well as driving directions. It also includes the walking route from the Ski Stadium back to the village.
We apologize for any inconvenience the construction work may cause to our visitors.